In a bid to achieve the Sustainable Development Goals (SDGs), the Nigerian government, through the Office of the Senior Special Assistant to the President on SDGs (OSSAP-SDGs), awarded contracts for several projects in Osun State, including building a 100-bed hospital in Osogbo, a transit home for abused women and an 80-bed hospital, both located in Iragbiji. Though completed and commissioned over a year ago, the multi billion-naira projects are wasting away despite the huge fortune spent to construct them. Visits to the project sites, in July 2023, by our reporter, LAWAL Sofiyyat Bolanle, show that they were under lock and keys with bushes taking over the buildings. There were also several issues observed regarding the contracts and their execution

On a cozy Thursday morning, Mrs Adebimpe Daniel, a trader whose kiosk is located adjacent the deserted hospital building in Osogbo, Osun State, bemoaned that the project has not served the host community since it was completed and commissioned over a year ago.

“Since the hospital was commissioned last year, they have not started working there, though it seems it has been equipped. There is a maternity home at Olude, a neighboring community, which is a bit far. There is a private hospital in this area but it is costly.” Adebimpe stated.

The project being referred to, the 100-bed capacity hospital in Osogbo, the Osun State Capital, is one of the projects awarded in Osun State by the Office of the Senior Special Assistant to the President on Sustainable Development Goals (OSSAP-SDGS) in 2021 under the leadership of Adejoke Orelope-Adefulire, who was recently reappointed to the same role by President Bola Tinubu.

In 2015, the United Nations adopted the 17 Sustainable Development Goals (SDGs) aimed at tackling global challenges to create a sustainable and habitable environment for people around the world. The third of the 17 SDGs aims to ensure healthy lives and promote well-being for all. It has a number of targets and topping the list is reduction of
the rate at which pregnant women and new mothers die after childbirth to 70 per 100,000 live births by 2030 but currently, the maternal mortality ratio in Nigeria is 1,047 per 100,000 live births.

Between 2000 and 2015 when the SDGs transformed to the Millennium Development Goals (MDGs), Nigerian mortality rate reduced by 30.4% from 1,174 deaths to 814 deaths per 100,000 live births. Even with this notable reduction, the country was unable to meet the MDGs target. According to the World Health Organization, the maternal death rate, which revolves around post-abortions, child births, postnatal and prenatal care is 1 in 22 in Nigeria, unlike developed countries with 1 in 4900. Globally, Nigeria is among the countries with the highest maternal death rate of nearly 20%.

In a bid to achieve the SDG in Osun State, the federal government, through the OSSAP-SDGs awarded contracts for the provision of a 100-bed mother and child hospital in Osogbo, an 80-bed hospital located in Iragbiji and a Transit Home for abused women. The Transit Home, which has an admin block, a skill acquisition center and a 100-seater canteen, is located beside the 80-bed hospital in Iragbiji. The projects have been completed but are, curiously, currently locked up and left to rot away.

According to information on Govspend, a website that provides data on Federal Government expenditures, the sum of N2.53billion was released for the projects between 2021 and 2022. The projects were commissioned on June 29, 2022 and have since been handed over to the Osun State government.

 

Ineffective Multi-million naira hospitals
Visits to the sites of the projects in July revealed the ineffective state of some of the facilities, as they had not been put to use over a year after they were commissioned.

During a visit to the 100-bed hospital at Oke Oni-tea, residents and shop owners in the area lamented the ineffectiveness of the hospital a year after it had been commissioned for use. Mrs Adebimpe Daniel, a trader in the area, said the hospital is affiliated to UNIOSUN Teaching Hospital (UTH), which “is meant to refer their patients here in case of insufficient space at their main hospital.”

A signage indicating that the 100-bed is under UTH management. Credit: LAWAL Sofiyyat Bolanle, PEN PRESS

Two security officers guarding the project site, who refused to identify themselves, denied this reporter access into the building. They said that they do not open the gate to anybody unless there is a directive from their boss. They also refused to disclose the identity or give out their boss’ phone number when asked by the reporter.

“We have been here for the past four months and we do not grant anybody entrance, not even the management of UTH unless we get a call from our boss. It is not within my power to grant you access and it would have been a different case if the hospital is functional, you would have been free to enter,” one of them said. The securities also declined the request of the reporter to share their boss’ contact.

While the contract for the construction of an 80-bed hospital located at Oke-Iragbiji in Iragbiji was similarly awarded by OSSAP-SDGs at the same time as the Osogbo hospital, to Wallbridge Global Impact Limited at the cost of N161.69 million, the construction of the 100-bed Mother and Child Hospital located beside Islahudeen Grammar School at Oke-Onitea in Osogbo was awarded to Mularabs Investment Limited at the cost of N205.63 million.

According to the CAC site, Mularabs Investment Limited, was registered on the 2nd of May, 2014 and is located at No 7, Enjema Road Ankpa, Kogi State with one Aminu ISA Yahaya as the director of the company.

Checks on the website of the Corporate Affairs Commission shows that Wallbridge Global Impact Limited, which executed the Iragbiji hospital project, was registered on the 28th of March, 2019 for general contract and merchandise and is currently inactive. The signage at the project site showed Ibukun’s House, No 637, Floor 1, Adetokunbo Ademola Street, Victoria Island, Lagos State, as the address of the company. Checks at the location, however, revealed that no company with the name exists there.

An Okada rider, Sesan Akinyemi, who identified himself as an indigene of Iragbiji lamented the non – use of the projects executed in the town. “I do not understand why the government chose to waste money. Why will they execute projects when they know they would not bring in people to work there?” he queried.

 

Previous Administration did not properly hand over the Transit Home to us
Another project of the OSSAP-SDGs in Iragbiji is a Transit Home for Abused Women which shares a fence with the 80-bed hospital. Despite the whooping sum of 699.4 million paid to contractors for the construction and equipping of the transit home, the compound of the home was seen to have been outgrown with bush. One could spot budding weeds sprouting out from the interlocking floor.

The transit home for abused women. Credit: LAWAL Sofiyyat Bolanle, PEN PRESS

Located at the extreme of the Transit Home is a solar-powered borehole. An administrative block is adjacent to the security post. Beside the skill acquisition center, a 250KVA Generator was sighted on the left side from the gate. The security man at the home granted the reporter access into the building dishing tidbits of what he knows about the project since he assumed work.

“My job here is to secure this place and grant no one entrance, not even my relatives. Nothing must go missing here. I am an officer of the Western Nigeria Security Network codenamed – Amotekun. I assumed work here last year,” he said while gesticulating with his index finger, trying to unsuccessfully recall the month he resumed work there.

He added that he was there during the commissioning of the project in June 2022. “I secure the whole compound. The government employed me and my colleagues. This place has been equipped,” he added.

In a chat with the spokesperson of Osun State Governor, Mr Olawale Rasheed, he told the reporter that the past administration failed to do proper handing-over of the Transit Home to the new government.

“The previous administration did not properly hand over the Transit Home to us. Our team only took possession last month. Inspection was conducted by three commissioners and the Special Adviser on SDGs. Though it is still ongoing, the team is taking inventory of equipment at the complex and it was noticed that the skill acquisition center is well equipped. The equipment are not in bad shape though they have been locked up for a long time,” he said.

Bushes competing with the Skill acquisition Center. Credit: LAWAL Sofiyyat Bolanle, PEN PRESS

When asked when work will start at the Transit Home, he told PEN PRESS that the place will be ready for use in no time. “There are beds, computer sets among other equipment at the place and the centre is being prepared for usage.” He concluded.

 

Flaws in the Procurement Process
Contract for fencing, interlocking, gate and access road to the 100-bed hospital were awarded to Tuncy & Co Limited at the cost of N160.35 million. The company was registered on October 8, 2020 for general contracts and merchandise. It got its first interim payment of N115,928,508 on the 13th March, 2022, which is a year and 7 months after registration date and hereby could not have tendered a tax clearance certificate which is obtainable three years after assessment of a company according to section 85(1) of the Personal Income Tax (PIT) Act.

Tuncy & Co signage at the 100-bed hospital. Credit: LAWAL Sofiyyat Bolanle, PEN PRESS

According to the CAC portal, Tuncy & Co Limited is located at Section F, House 27, 1k Road, Federal Housing Estate, Lugbe, Abuja. However, findings show that the said address is either a home or church. Attempt to speak with the inhabitants was futile as the repeated knocks on the gate were left unanswered during a visit to the location. Prior to the visitation, an email sent to the company’s email address provided on the CAC portal was not replied.

It was observed that the access road that links the main road to the hospital had not been constructed despite paying the contractor for it.

Furthermore, the contract for the 200-capacity transit home was awarded to Bay-mage Consults Limited at N214,639,865. Bay-mage Consults Limited was registered on August 24, 2020, specifically for computer programming, consultancy and related activities. The company got the first interim payment on December 18, 2021, just a year and 4 months after its registration, and, thus, would have violated the same section of the PIT Act as Tuncy & Co Limited. Unfortunately, the address on the CAC portal was under renovation when visited and the residents of the area could not identify the owners or where they relocated to.

The sum of N21.23 million was paid to Kaffog Industrial Company Limited to construct two solar powered boreholes at the Transit Home and the 100-bed hospital. The firm was registered on October 5, 2020, purposely for general contract and merchandise. Though the boreholes have been dug but has not been put to use.

These companies might have violated section 16(6d) of the Public Procurement Law (2007), which states that: “All bidders, in addition to the requirements contained in the solicitation documents, shall fulfill all its obligation to pay taxes, pensions and social security contributions.

 

Unregistered entity awarded contract
However, Arhos Nigeria Limited, a non-registered company under CAC, was found to have been paid a sum of N46.52 million for the supply of furniture to the 100-bed hospital. Checks on the CAC portal, Ng-Check and B2BHint showed other companies with very similar names including Arho Nigeria Limited and Arhos and Sons International Nigeria Limited, but nothing on Arhos Nigeria Limited.

The construction and installation of 100 solar street lights, 50 each to the 100-bed hospital and 80-bed hospital was awarded to CWM Contracting at the sum of N101.50 million.

Though the street lights could be sighted at the project’s sites, CWM is a registered and inactive company under CAC. Mails have been sent to the persons in control, Mr Anjorin Adebayo and Afolabi Samson Olatunji, which are yet to be replied.

Jls Brothers Limited, an Abuja-based company was contracted and paid to do the fencing, interlocking pavement and walkway at the Transit Home for a sum of N51,086,539. However, the place is partly interlocked and the home was seen to have been outgrown with bushes. The same company was also awarded the construction of a 100-seater canteen in the home at the cost of N60.33 million.

The admin block of the transit home. Credit: LAWAL Sofiyyat Bolanle, PEN PRESS

According to the CAC website, Jls brothers Limited was registered on October 24, 2017 specifically for general contracts and is located at Plot 333, Airport Road. A search to trace the company is futile as it is not located on the said address.

Other contracts awarded as part of the project include: Huzaimas Nigeria Limited, registered on August 20, 2017, was paid the sum of N46.35 million to supply furniture. According to the information on the CAC portal, the company is inactive and the persons in control of the company, Aminu Abdullahi and Ibrahim Muhammad failed to provide their email addresses.

Construction and installation of 140KVA hybrid Solar inverter at 100-bed hospital was awarded to 25th Investment Ltd. The company, registered on the 30th April 2019 is inactive. Also 80KVA hybrid solar inverter construction and installation contract for the Iragbiji facility was awarded to Bmo-tech Services Limited at N117.61 million, a company registered on October 8, 2020 and contracted for this project 2nd of February 2, 2022.

Tru3 Nigeria Limited and Mba & Company Limited were paid the sum of N166.27 million each to supply and install theatre equipment to the 80-bed and 100-bed hospitals respectively. Also, Tappago Engineering Limited was paid a sum of N36.35 million to supply 208 laminated 4 by 4 boarded beds with mattresses, pillows and lockers to the Transit Home for Abused Women.

Equipping of the acquisition center with fashion designing, salon, refrigeration and building trade was done by Olu-omo Integrated Services Limited at a sum of 52.35million. The company, which is controlled by Idris Balogun and Funke Balogun was registered on the 15th of October, 2008 and is currently inactive under CAC.

In all, the total sum for the construction and equipping of the 80-bed hospital was evaluated to be about 748.45 million, while 1.059 billion was released for the construction and equipping of the 100-bed hospital.

An aide to Orelope-Adefulire, Desmond Utomwen, while responding to the findings said the companies were duly registered. “You may want to reach out to them. I can assure that there is no cause for alarm. From all the available records in the office, the companies were duly registered.” He however declined to answer further enquiry on the status of the companies that were awarded contracts by the OSSAP-SDGs and the bidding process.

 

Budget splitting and inflation
A sum of N31.43 million was paid to Corredor Business Network Limited for the provision and installation of 15 incubating equipment – 10 to the 100-bed hospital in Osogbo and 5 to the 80-bed hospital in Iragbiji. Investigations show that only ten of these were supplied. However, a similar contract for the provision and installation of 15 incubating equipment with the same sharing formular was awarded to Telefonica Blizzard Company Limited at the cost of N11.98 million. The company is located at No 2, Ikeja Close, off OYO Street, Garki Area 2. Aretta Anah and Debate Egbede are listed as directors of the company which is currently inactive on the CAC portal.

The wide difference in the both contract amounts (Corredor Business Network Limited got the same Contract for almost thrice the amount as Telefonica Blizzard Company Limited) also points to possible inflation to the contract awarded to Corredor Business Network Limited. Both contractors were paid on August 31,2022, according to information on Govspend.

In another case of contract splitting, three different companies were awarded the same contract to supply the hospitals in Osogbo and iragbiji with automated beds. The contract for the supply of 50 specialized automated beds – with a distribution ratio of 40:10 between 100-bed hospital and 80-bed hospital – was awarded to Tafskad All Round Service Limited at N43.25 million.

Another contract for the supply of 50 complete sets of specialized hospital beds with mattresses and pillows and bedside lockers to the 80-bed hospital at Oke-iragbiji was awarded to Sukeem Nigeria Limited at the same N43.25 million.

A third contract for the provision of 50 complete specialized automated hospital beds with mattresses, pillows and lockers to the 100-bed hospital was awarded to Covenant Plus Engineering Limited at N43.25 million. The contract splitting of these project is obvious as the three companies were paid the same amount, with two of them getting paid on the same date while the third company got its payment a day after.

This obvious contract splitting is contrary to the provisions of the Public Procurement Act (2007). Section 58(4d) of the Public Procurement states that: “The following shall also constitute offenses under this Act; splitting of tenders to enable the evasion of monetary thresholds set.”

 

Possible inflation of contract?
Bmo-tech Services Limited was paid to supply and install two 250KVA sound-proof generators at the cost of N107.20 million, in which one is meant to be supplied to the 100-bed hospital. Similarly, another company, Grand Performer Limited, was awarded a contract to provide and install three 250 KVA sound-proof generators at N160.53million, from which a generator is meant to be at the 80-bed hospital in Iragbiji.

When asked the designated location of the second generator, the director of the Bmo-tech Services Limited, Mr Olojotuyi Bamidele Segun, declined to provide an answer, and directed the reporter to OSSAP-SDGS.

“OSSAP-SDG awarded these contracts, provided the locations/end users and supervised the execution. Concerning our eligibility to be awarded a contract, I will suggest you visit the procurement unit of OSSAP-SDGS to obtain our tender documents, which I know will put a rest to your questions and enquire,” he stated.

No information could be obtained from Grand Performer Limited Directors on the generators it supplies as the company failed to respond to an email sent to its listed email address.

Asides that the locations of the other three generators are unknown, checks by our reporter showed that the market value of a 250KVA sound-proof generator (Perkins model) is N15.5 million, according to Jumia. This shows that there is an inflation in the amount these projects were contracted.

 

What is the use of an open visionless eye?
The Baale of Oke Iragbiji, Gbadebo Abolarinwa, noted that work on the 80 – bed hospital and abused women home was completed almost two years ago, and that they had been equipped with state-of-the-art facilities before the projects were commissioned last year. He lamented the unproductive state of the hospital that could have been useful for the residents.

80-bed hospital, Iragbiji. Credit: LAWAL Sofiyyat Bolanle, PEN PRESS

“I was there when they were commissioned. They were well equipped with good facilities and equipment which include sewing machines, hospital beds and many more. There are many hospitals in town though the SDGs projects would have been of great benefit to the residents of Iragbiji if it were functioning but it is currently useless. What is the use of an open visionless eye?” The local chief asked rhetorically.

He stated that a new private health facility in the area has been tending to the health needs of residents of the town. He urged the Government to bring in professionals so the facilities could be useful to his community and save the equipment in the facilities from wasting away.

“As it is now, the hospital is not useful and it would be better if medical practitioners were mobilized to the hospitals. There is no way residents will not patronize even if they are meant to pay a token. I hope the equipment are still in good condition,” he concluded.

Hospitals inefficient due to bad structures
Desmond Utomwen, a media aide to Orelope-Adefulire, said the projects have since been completed and handed over to the state government.

“The projects in question have since been completed, commissioned and handed over to the state for use in the interest of the people in Osun.” Utomwen stated in a chat with PEN PRESS.

The UNIOSUN Teaching Hospital does not dispute that two of the facilities have been handed to it. Its position is that the facilities do not have what it takes to make them function.

Uniosun Teaching Hospital Entrance. Credit: Taiwo Fatola

In an interview with the Chief Medical Director of UNIOSUN Teaching Hospital, Professor Peter Olaitan, he confirmed that the two hospitals have been handed over to UTH since August 2022. He, however, added that the transit home for abused women project was not handed over to UTH.

While responding to enquiries on what has been holding UTH back from working in the hospitals, he attributed it to the bad structure of the building and lack of electricity in the new facilities.

“Two hospitals were actually handed over to us, that is the 80-bed hospital in Iragbiji and the 100-bed hospital in Osogbo. There are quite a number of things that will make a hospital work. For example, there was no link to electricity source. The only thing we have there are generator and solar inverters. Also the laboratory at the Oke Oni-tea in Osogbo is too small to accommodate pathologists, microbiologists and even blood bank. There is no laundry room, no kitchen and no ambulance.” Professor Olaitan said during the interview.

He added that there was a time when the roof of the 100-bed hospital was blown off and that the hospital had to use out of its own money to fix it after the contractor failed to respond to their calls.

“The thing was getting worse and worse and the equipment was getting spoilt, so we decided to fix it.” He added.

“Due to the non-functional state of the hospital, the solar batteries and panels were destroyed. The solar batteries were bad and they were quite heavy batteries that needed a lot of money. And solar panels too, a lot of them were already removed by rainstorm. As for the hospital in Iragbiji, the roof was terribly leaking, so we couldn’t use it until last week when it was fixed.” Olaitan stated.

In order to make the hospitals efficient and effective, Professor Olaitan said UTH reached out to the state government about the challenges faced at the new facilities. “Though it’s not enough, we got some funds from the government. We have gotten an ambulance and some laboratory equipment. We also look forward to providing a waiting room for patients and their relatives, as well as a kitchen and laundry room.” He concluded.

“To get the hospitals working, a sum of ₦ 400 million will be needed.” He said when asked to estimate the amount it would cost to get the hospitals functioning.

 

Health Expert Reacts
Dr Solomon Ilori, a Chief Registrar at the Department of Obstetrics and Gynecology at UNIOSUN Teaching Hospital likened the state of the projects to a good-for-nothing car. He added that the management of UNIOSUN Teaching Hospital is working effortlessly to achieve the purpose of the hospitals.

While speaking on the slow response of the management, Dr Ilori told PEN PRESS that the management is challenged with insufficient personnel and the structure of the building which they are still trying to adapt to, since it was not suitable enough.

“I am aware of the projects at Oke Oni-tea and Iragbiji. I followed the management as the Chief registrar of the Department to check the infrastructures that are there. Good buildings but no health care professionals. A car is as good as nothing when it has no driver,” Ilori said.

He added that the effects of the redundant facilities are borne by the citizens.

“The buildings cannot serve the immediate environment so it is useless. Imagine someone from Iragbiji has an Obstetrics & Gynecology emergency, like a case of bleeding after childbirth or heavy menstrual bleeding, instead of the facilities to serve such patients, they would have to be rushed down to Osogbo. There have been times when people with such conditions are brought in dead,” he added.

While commenting on the way forward in the Nigerian health sector, he charged the Federal Government to implement sustainable healthcare policies. “The abandoned structures are not the issue but the commitment of the government towards healthcare. The healthcare policies are summarily unbearable.” The gynecologist stated.

 

CSOs React
Olarenwaju Suraju, the Chairman of HEDA Resource Centre, an organization with mandate on anti-corruption, good governance, accountability, environmental justice and human rights, said a company should only be awarded contracts based on its diligent records.

“Any company with the evidence of payment of taxes as and when due, with proven competence and capacity to execute a contract should get it if they meet the requirements,” Mr Suraju stated in an interview with PEN PRESS.

He, however, faulted the CAC agents that registered a company without a traceable address.

“Many companies get registered presenting fake proof of address and the registering authorities are compromised or lack capacity to verify documents.”

He concluded by enjoining the enforcement of the law and prosecution of the perpetrators. “The Corporate Affairs Commission needs to do background checks on the registered companies from time to time.” He stated and concluded by suggesting that the punishment for law breakers should be enforced.

 

*This investigation is supported by the John D. and Catherine T. MacArthur Foundation and the International Centre for Investigative Reporting.